Operation of small
isolated power system with large non-controllable RES penetration
System Operators experience in El Hierro Island
R. Corujo, P. Santos and R. Ascanio
2019/07/15
|

Abstract
The Canary Islands are facing a transitiontowards
renewable energy, in an attempt to build a cleaner and cheaper power system
for the coming years.
This transition poses a big challenge for the TSO that will face the operation
of weak grids, with a large amount of non-controllable generation, in
a context of reduced natural inertia.
In this context the methodology and operational criteria of El Hierros
power system, operated by the TSO, are to maximize the amount of renewable
energy in a safe way, minimizing the risks associated with the unpredictability
of wind-power, and to do so minimizing the electrical power generation
cost.
This paper shares the REE experience in the operation of a small isolated
power system with large non-controllable RES that, as a result, has established
a new record in 2018, where the the pumped storage hydro facility named
Central Hidroeólica de El Hierro (CHE) covered the complete islands
demand during 18 consecutive days, more than two weeks where the diesel
power plant was completely off and the island was therefore 100% renewable.
| Published in: Renewable Energy
& Power Quality Journal (RE&PQJ, Nº. 17) |
| Pages: 128-132 |
Date of Publication: 2019/07/15 |
| ISSN: 2172-038X |
Date of Current Version:2019/04/10 |
| REF: 242-19 |
Issue Date: July 2019 |
| DOI:10.24084/repqj17.242 |
Publisher: EA4EPQ |
Authors and affiliations
R. Corujo1, P. Santos1 and R. Ascanio1
1. Isolated System Department Red Eléctrica de España S.A.U.
(REE). Alcobendas, Madrid (Spain)
Key words
Isolated systems, TSO, RES, storage, pumped hydro.
References
[1] K.D. Orwig, M.L. Ahlstrom, V. Banunarayanan, J. Sharp,
J.M. Wilczak, J.F. Freedman, S.E. Haupt, J. Cline, O. Bartholomy, H.F.
Hamann, B.M. Hodge, C.Finley, D. Nakafuji, J.L. Peterson, D. Maggio, M.
Marquis, Recent Trends in Variable Generation Forecasting and Its
Value to the Power System, in Proc. IEEE TRANSACTIONS ON SUSTAINABLE
ENERGY 2015.
[2] A. Marrero, E.J. Medina, J.M. de León, 2018, Gorona del
Viento Wind-Hydro Power Plant Results, Improvement Actuations and Next
Steps, in Proc. 3rd International Hybrid Power System Workshop 2018.
[3] M. Pezic, V. Moray, Unit Commitment in Fully Renewable Hydro-Wind
Energy System, 2013.
[4] P. Tielens, D. Van Hertem, Grid Inertia and Frequency Control
in Power Systems with High Penetration of Renewables, in Proc. Young
Researchers Symposium in Electrical Power Engineering, 2012.
[5] N. Taveira, J. Palomares, E. Quitmann, The Hybrid Power Plant
in El Hierro Island: Facts and Challenges from the Wind Farm Perspective,
in Proc. 3rd International Hybrid Power System Workshop 2018.
[6] C.A. Platero, C. Nicolet, J.A. Sánchez, B. Kawkabani, Increasing
wind power penetration in autonomous power systems through no-flow operation
of Pelton turbines, , in Proc. Renewable Energy 2014.
[7] J.I. Sarasúa, G. Martínez-Lucas, C.A. Platero, J.A.
Sánchez-Fernández, Dual Frequency Regulation in Pumping
Mode in a Wind-Hydro Isolated System in Proc. Energies 2018.

|
|